Commercial Substantially complete 2026

Storefront stucco repair & decorative finish — Stuyvesant Plaza

Hirsch Construction Corp. (GC) for a national mattress retailer · 1475 Western Avenue, Albany, NY

Subcontractor to the general contractor

EIFS & stucco

The storefront columns and band before the stucco repair and decorative finish, August 2026
The storefront columns and band before the stucco repair and decorative finish, August 2026

Scope

Repair of the existing storefront stucco, CMU and EIFS at a plaza tenant space, two site-matched decorative finish colors, and a change order for additional finish-coat areas — billed through the GC's Procore requisitions with COI compliance managed through the GC's insurance portal.

Challenge
A retail schedule with other trades in the storefront, insurance requirements written for a national program, and colors that had to match samples approved on site.
Solution
Finish samples matched and approved in the field, work sequenced around the storefront glazing, and certificates issued with every additional insured the program required.
Result
Base scope and change order complete; exterior punch list scheduled with the tenant for mid-September 2026.

2 photographs — before, during and after. Click any photo to enlarge.

More projects like this

All projects
After: the repainted grandstand from the field, July 2026
Public works Complete 2026

Casey Stadium — exterior steel & EIFS repaint

University at Albany (SUNY) · Albany, NY

Prime contractor — competitively bid, bonded, prevailing wage

Complete exterior repaint of the stadium's structural steel — seating supports, railings, stair stringers and canopies — and of its EIFS wall surfaces, in the university's purple and gold. Steel: cleaning and pressure washing of chalked coatings, mechanical removal of failed film, epoxy spot-priming of rust at base plates and welds, and waterborne alkyd-urethane enamel topcoats. EIFS: pressure washing, crack and impact repair, and a breathable elastomeric masonry coating matched to the campus colors. Change-order work included the box-office canopy and an additional guardrail.

Coatings & paintingEIFS & stucco

After: the finished equipment island under the garage deck, August 2026
During: forms, reinforcing mat and conduit stub-ups, August 2026During: island placed by trailer pump and finishedDuring: one of four equipment pads on grade, formed with rebar and conduit
Commercial Complete 2026

Pay-for-parking equipment island

Ellis Medicine · 1101 Nott Street, Schenectady, NY

Prime contractor under hospital purchase order

A new reinforced concrete island under the parking-garage deck for the hospital's pay-station equipment, tapering from six to twelve inches to follow the slope, plus four equipment pads on grade, steel bollards and conduit stub-ups for the electrical contractor. Asphalt cut, existing slab exposed, mats set and concrete placed by trailer pump.

Concrete

After: brick retaining wall pressure-washed and efflorescence removed, July 2026
Before: efflorescence on the same wall, July 2026After: a replaced sidewalk panel, August 2026Before: heaved, spalled panel on a route to the emergency department
Commercial Complete 2026

Sidewalk replacements & retaining-wall cleaning

Ellis Medicine · Nott Street and Rosa Road, Schenectady, NY

Prime contractor under hospital purchase orders

Three full sidewalk panel replacements and seven interim patch repairs on the hospital campus; pressure washing and efflorescence removal on brick retaining walls; trip-hazard grinding on the Rosa Road sidewalk. A further purchase order for site-wall washing and coping-stone reset follows in fall 2026.

ConcreteRestoration & waterproofing

Next step

Have a project or a bid package?