Commercial Substantially complete 2026

Storefront stucco repair & decorative finish — Stuyvesant Plaza

Hirsch Construction Corp. (GC) for a national mattress retailer · 1475 Western Avenue, Albany, NY

Subcontractor to the general contractor

EIFS & stucco

The storefront columns and band before the stucco repair and decorative finish, August 2026
The storefront columns and band before the stucco repair and decorative finish, August 2026

Scope

Repair of the existing storefront stucco, CMU and EIFS at a plaza tenant space, two site-matched decorative finish colors, and a change order for additional finish-coat areas — billed through the GC's Procore requisitions with COI compliance managed through the GC's insurance portal.

Challenge
A retail schedule with other trades in the storefront, insurance requirements written for a national program, and colors that had to match samples approved on site.
Solution
Finish samples matched and approved in the field, work sequenced around the storefront glazing, and certificates issued with every additional insured the program required.
Result
Base scope and change order complete; exterior punch list scheduled with the tenant for mid-September 2026.

2 photographs — before, during and after. Click any photo to enlarge.

More projects like this

All projects
After: the repainted grandstand from the field, July 2026
Public works Complete 2026

Casey Stadium — exterior steel & EIFS repaint

University at Albany (SUNY) · Albany, NY

Prime contractor — competitively bid, bonded, prevailing wage

Complete exterior repaint of the stadium's structural steel — seating supports, railings, stair stringers and canopies — and of its EIFS wall surfaces, in the university's purple and gold. Steel: cleaning and pressure washing of chalked coatings, mechanical removal of failed film, epoxy spot-priming of rust at base plates and welds, and waterborne alkyd-urethane enamel topcoats. EIFS: pressure washing, crack and impact repair, and a breathable elastomeric masonry coating matched to the campus colors. Change-order work included the box-office canopy and an additional guardrail.

Coatings & paintingEIFS & stucco

After: the cleaned and repointed limestone front of the Wedgeway, October 22, 2026
Commercial Complete 2026

Wedgeway & Kresge Buildings — limestone facade restoration & cleaning

Cass Hill Development Co. · Schenectady, NY

Prime contractor under owner purchase order

Exterior restoration of two adjoining downtown buildings at 271–277 State Street: repointing of every failed joint in the Wedgeway's limestone front with a color-matched Type N mortar, restoration cleaning (PROSOCO masonry cleaners) and sealing of the stone, rebuilding of two damaged stone corners, cleaning and repainting of the marquee steel, first-floor stucco/EIFS repair matched to the existing color and texture, and facade cleaning and EIFS repair on the Kresge building next door.

Restoration & waterproofingMasonryEIFS & stuccoCoatings & painting

The Argus Building clock tower, seen from the lift, September 2026
Commercial Complete 2026

The Argus Building — historic cornice & tower clock restoration

Building owner, through the project's general contractor · Albany, NY

Restoration subcontractor

Localized restoration at the top of the Argus Building, 412 Broadway at Beaver Street: removal of rotted soffit, fascia and decorative wood brackets at the cornice; replacement members milled to match the existing 19th-century profiles; epoxy consolidation of the wood worth saving; and restoration of the tower clock face — new custom-cut round glass, repaired wood surround and trim, hands re-set — all primed and left weather-tight.

Restoration & waterproofing

Next step

Have a project or a bid package?