Commercial Complete 2026

Pay-for-parking equipment island

Ellis Medicine · 1101 Nott Street, Schenectady, NY

Prime contractor under hospital purchase order

Concrete

After: the finished equipment island under the garage deck, August 2026
After: the finished equipment island under the garage deck, August 2026

Scope

A new reinforced concrete island under the parking-garage deck for the hospital's pay-station equipment, tapering from six to twelve inches to follow the slope, plus four equipment pads on grade, steel bollards and conduit stub-ups for the electrical contractor. Asphalt cut, existing slab exposed, mats set and concrete placed by trailer pump.

Challenge
Working inside an active hospital parking garage with traffic control, low headroom for placement, and a slab that turned out to be twelve inches thick on one side and five on the other.
Solution
Barricaded work zone, pump placement, and a crack-resistant mix with reinforcement set to suit the varying depth.
Result
Complete and invoiced August 2026 — one of several 2026 purchase orders from the hospital's facilities department.

4 photographs — before, during and after. Click any photo to enlarge.

More projects like this

All projects
After: the cleaned and repointed limestone front of the Wedgeway, October 22, 2026
Commercial Complete 2026

Wedgeway & Kresge Buildings — limestone facade restoration & cleaning

Cass Hill Development Co. · Schenectady, NY

Prime contractor under owner purchase order

Exterior restoration of two adjoining downtown buildings at 271–277 State Street: repointing of every failed joint in the Wedgeway's limestone front with a color-matched Type N mortar, restoration cleaning (PROSOCO masonry cleaners) and sealing of the stone, rebuilding of two damaged stone corners, cleaning and repainting of the marquee steel, first-floor stucco/EIFS repair matched to the existing color and texture, and facade cleaning and EIFS repair on the Kresge building next door.

Restoration & waterproofingMasonryEIFS & stuccoCoatings & painting

The Argus Building clock tower, seen from the lift, September 2026
Commercial Complete 2026

The Argus Building — historic cornice & tower clock restoration

Building owner, through the project's general contractor · Albany, NY

Restoration subcontractor

Localized restoration at the top of the Argus Building, 412 Broadway at Beaver Street: removal of rotted soffit, fascia and decorative wood brackets at the cornice; replacement members milled to match the existing 19th-century profiles; epoxy consolidation of the wood worth saving; and restoration of the tower clock face — new custom-cut round glass, repaired wood surround and trim, hands re-set — all primed and left weather-tight.

Restoration & waterproofing

After: new entry stairs, accessible ramp and steel guardrails, June 2026
Public works Complete 2026

Nathan Lebron Early Learning Center — concrete stairs, ramps & ADA railings

Albany Community Action Partnership (ACAP) · 170 Ontario Street, Albany, NY

Prime contractor — competitive proposal

Replacement of concrete entry stairs, landings and accessible ramps at an occupied early-learning center, followed by a change order for new code-compliant steel pipe guardrails and handrails required by the building department's ADA review. Permit application and stair-layout drawings prepared by TDCG.

Concrete

Next step

Have a project or a bid package?

Send us the plans, the RFP link or a few photos. You'll get a site visit scheduled and a written proposal — and a certificate of insurance within one business day when you need one.