Commercial Complete 2026

1 Columbia Street — parapet flashing, stairwell repairs & window sealing

Cass Hill Development Co. · Albany, NY

Prime contractor (repeat client)

Restoration & waterproofing

Before: the parapet and coping from the roof, June 2026
Before: the parapet and coping from the roof, June 2026

Scope

Pipe scaffold access with netting to replace the parapet flashing on a downtown mixed-use building; interior water-damage repairs in the Stair 2 stairwell (cement plaster basecoat, sheetrock, plaster and paint); exterior perimeter sealing at three windows.

Challenge
During the flashing work the crew found siding installed directly over bare sheathing with no water-resistive barrier — a condition outside the contract that explained the leaks.
Solution
Written notice with photos the same day, a recommended fix (remove siding, install a WRB, re-clad), and the contracted flashing scope completed without over-promising on the outcome.
Result
All three scopes complete and invoiced September 2026.

6 photographs — before, during and after. Click any photo to enlarge.

More projects like this

All projects
After: the rebuilt and repointed north elevation, August 2026
Public works Complete 2026

332 Ninth Street — north elevation masonry rebuild

Troy Community Land Bank Corporation · Troy, NY

Prime contractor — RFP award, contract executed with the land bank board; masonry subcontracted

Repair and partial rebuild of a deteriorated north-elevation masonry wall on a land-bank-owned building: selective demolition, brick rebuild and repointing, helical-tie anchoring per the engineer's details, and City of Troy permitting and insurance requirements. Masonry by our subcontracted mason under TDCG supervision.

MasonryRestoration & waterproofing

After: the finished equipment island under the garage deck, August 2026
During: forms, reinforcing mat and conduit stub-ups, August 2026During: island placed by trailer pump and finishedDuring: one of four equipment pads on grade, formed with rebar and conduit
Commercial Complete 2026

Pay-for-parking equipment island

Ellis Medicine · 1101 Nott Street, Schenectady, NY

Prime contractor under hospital purchase order

A new reinforced concrete island under the parking-garage deck for the hospital's pay-station equipment, tapering from six to twelve inches to follow the slope, plus four equipment pads on grade, steel bollards and conduit stub-ups for the electrical contractor. Asphalt cut, existing slab exposed, mats set and concrete placed by trailer pump.

Concrete

After: brick retaining wall pressure-washed and efflorescence removed, July 2026
Before: efflorescence on the same wall, July 2026After: a replaced sidewalk panel, August 2026Before: heaved, spalled panel on a route to the emergency department
Commercial Complete 2026

Sidewalk replacements & retaining-wall cleaning

Ellis Medicine · Nott Street and Rosa Road, Schenectady, NY

Prime contractor under hospital purchase orders

Three full sidewalk panel replacements and seven interim patch repairs on the hospital campus; pressure washing and efflorescence removal on brick retaining walls; trip-hazard grinding on the Rosa Road sidewalk. A further purchase order for site-wall washing and coping-stone reset follows in fall 2026.

ConcreteRestoration & waterproofing

Next step

Have a project or a bid package?